NEED MORE INFO? QUICK QUESTION
A specialist advisor will get back to you asap.
In 1999, the Bangkok Metropolitan Authority reconstructed the iconic Ratchadamnoen Klang Road. The total area for the road rehabilitation project covered 8,000 m2. The pavement was constructed over a 30-day period during November 1999.
The degraded asphalt pavement was demolished and stockpiled. The in-situ soil (very soft clay) was excavated to the required depth. The stockpiled old asphalt pavement material was recycled as the new sub-base and compacted to a depth of 150mm.
A new 300mm base layer was constructed from crushed rock stabilised with cement and Renolith. The crushed rock, cement and water were combined at a mixing plant and transported to site via ready-mixed concrete truck. Renolith admixture was added to mix at site. The base material was laid and compacted. The mix design for the base layer was:
An asphalt wearing surface was applied to a depth of 50mm.
Major plant for this project consisted of a back-hoe, grader, roller compactor and ready-mixed concrete truck.
The total cost was 3,200,000 Baht (400 Baht per sqm) – roughly $140,000 AUD (or AUD$17 per sqm) in 1999. This equates to approximately AUD$34 per sqm in 2024 when adjusted for inflation.
Ratchadamnoen Klang Road, Bangkok – 1999
Using Google Earth – street view it is possible to inspect the current state of the pavement. The road appears to be in very good condition a quarter of a century later.
The project was very successful in all key aspects:
Crushed rock was stabilised with Renolith and cement to form the base layer for the Ratchadamnoen Klang Road. The construction process was fast, low-cost and low-carbon. The pavement remains in very good condition after more than 25 years – a truly sustainable outcome.
A specialist advisor will get back to you asap.